14130 W RIVERSIDE DR 91423
APPLICATION / PERMIT NUMBER: 19016-10000-39265
PLAN CHECK / JOB NUMBER: B19LA25920

Plan Check and Permit Information


GROUP: Building
TYPE: Bldg-Alter/Repair
SUB-TYPE: Commercial
PRIMARY USE: (13) Office
WORK DESCRIPTION: MAJOR REMODEL OF 3-STORY OFFICE/RESTAURANT/PARKING BLDG. INTO OFFICE AND PARKING ONLY BLDG. PER VTT 72802 AND CPC 2014-136-ZC-MCUP-SPR. CORE AND SHELL ONLY. INCLUDES NEW ATTACHED CANOPIES AND ROOF COVERING OVER (E) COURTYARD. (2017 LABC)
PERMIT ISSUED: Yes PERMIT ISSUE DATE: 07/18/2022 ISSUING OFFICE: Metro
CURRENT STATUS: Issued CURRENT STATUS DATE: 07/18/2022

Permit Application Status History
Submitted 12/09/2019 APPLICANT
Assigned to Plan Check Engineer 01/09/2020 LAWRENCE QUIRANTE
Corrections Issued 01/29/2020 LAWRENCE QUIRANTE
Quality Review Completed 02/03/2020 ALLEN MANALANSAN
Building Plans Picked Up 02/03/2020 APPLICANT
Disabled Access Plans Picked Up 02/06/2020 APPLICANT
Green Plans Picked Up 06/25/2020 APPLICANT
Applicant returned to address corrections 07/07/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 07/09/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 07/15/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 07/17/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 07/21/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 07/24/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 07/27/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 07/29/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 08/07/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 08/10/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/05/2020 LAWRENCE QUIRANTE
Applicant returned to address corrections 02/25/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 03/01/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 03/03/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 04/28/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 05/04/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 05/21/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 06/08/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 08/26/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 09/08/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 09/09/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 09/10/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/14/2021 LAWRENCE QUIRANTE
Plan Check Approved 07/14/2022 LAWRENCE QUIRANTE
Issued 07/18/2022 APPLICANT

Permit Application Clearance Information
Green Code Cleared 06/25/2020 LAWRENCE QUIRANTE
Low Impact Development Cleared 01/26/2021 AMMAR ELTAWIL
DAS Clearance Cleared 06/15/2021 ELIZABETH TOMS
Internal circulation Cleared 06/21/2021 SHEILA AHORAIAN
Disturb/Remove Protected Trees Cleared 06/24/2021 ADRIAN SANCHEZ
Supp. Use District POD/CDO/TDO Cleared 08/12/2021 RUBEN VASQUEZ
Hydrant and Access approval Cleared 03/31/2022 KURT CORRAL
Fire Marshall Fire Life Safety Cleared 04/20/2022 WILLIAM JOHNS
Eng Process Fee Ord 176,300 Cleared 04/22/2022 LEE GUILBEAUX
Permit Cleared 04/22/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 04/22/2022 LEE GUILBEAUX
Sewer availability Cleared 04/22/2022 LEE GUILBEAUX
CPC Cleared 05/20/2022 WILLIAM LAMBORN
Tract Map conditions Cleared 05/20/2022 WILLIAM LAMBORN

Licensed Professional/Contractor Information
Architect Information
Ball,, Larry Roy; Lic. No.: C12056
5112 TEESDALE AVE
VALLEY VILLAGE, CA  91607
Contractor Information
Imt Residential; Lic. No.: 766199-B
15303 VENTURA BLVD
STE. 200
SHERMAN OAKS, CA  91403
Engineer Information
Knur,, Reinard Thomas; Lic. No.: GE2755
1435 MONCADO DR
GLENDALE, CA  91207
Engineer Information
Powers,, Brian Frederick; Lic. No.: C75902
2090 WEST 31ST STREET
LOS ANGELES, CA  90018
Engineer Information
Zangoli,, Fabio; Lic. No.: S6191
13245 FIJI WY UNIT J
MARINA DEL REY, CA  90292

Inspection Activity Information

Inspector Information
CAMERON CHABAN, (818) 374-1128
Office Hours: 7:00-8:00 AM MON-FRI
ROBERT DAVIS, (818) 374-1128
Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspection Request(s)
  Deputy Reinf. Concrete   05/06/2024      Confirmation No.: 33276896

Inspection Request History
  Deputy Steel/Welding   09/15/2022   Conditional Approval   CAMERON CHABAN
  Deputy Steel/Welding   09/16/2022   Conditional Approval   CAMERON CHABAN
  Deputy Steel/Welding   09/20/2022   Conditional Approval   JEFFREY DURAN
  Deputy Steel/Welding   09/21/2022   Conditional Approval   JEFFREY DURAN
  Deputy Steel/Welding   09/22/2022   Conditional Approval   CAMERON CHABAN
  Deputy Steel/Welding   09/23/2022   Conditional Approval   JEFFREY DURAN
  Deputy Drilled-In Anchors   10/12/2022   Conditional Approval   CAMERON CHABAN
  Deputy Drilled-In Anchors   10/27/2022   Conditional Approval   ROBERT DAVIS
  Footing/Foundation/Slab   11/03/2022   Partial Approval   CAMERON CHABAN
  Deputy Drilled-In Anchors   12/05/2022   Conditional Approval   CAMERON CHABAN
  Deputy Other (see comments)   12/05/2022   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   01/20/2023   Conditional Approval   BRUCE CAMPBELL
  Deputy Shotcrete   01/23/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   01/24/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   01/25/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   01/26/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   01/27/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   01/30/2023   Conditional Approval   ANDREW DORSO
  Deputy Shotcrete   01/31/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   02/01/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   02/02/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   02/03/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   02/03/2023   Conditional Approval   STEVEN LEVITT
  Footing/Foundation/Slab   02/09/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   02/10/2023   Conditional Approval   CAMERON CHABAN
  Special/Order Compliance   02/10/2023   Conditional Approval   STEVEN LEVITT
  Green Building Rough   02/23/2023   Partial Inspection   CAMERON CHABAN
  Reinforced Concrete Frame   02/23/2023   Partial Approval   CAMERON CHABAN
  Excavation/Setback/Form/Re-Bar   03/09/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   03/14/2023   Conditional Approval   STEVEN LEVITT
  Deputy Shotcrete   03/22/2023   Conditional Approval   STEVEN LEVITT
  Deputy Shotcrete   03/23/2023   Conditional Approval   STEVEN LEVITT
  Deputy Shotcrete   03/24/2023   Conditional Approval   STEVEN LEVITT
  Deputy Shotcrete   03/28/2023   Conditional Approval   JEFFREY DURAN
  Deputy Shotcrete   03/29/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   03/30/2023   Conditional Approval   DEANDRE HOFFMAN
  Deputy Shotcrete   03/31/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   04/03/2023   Conditional Approval   CAMERON CHABAN
  Green Building Rough   04/03/2023   Partial Inspection   CAMERON CHABAN
  Reinforced Concrete Frame   04/03/2023   Partial Approval   CAMERON CHABAN
  Deputy Shotcrete   04/04/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   04/05/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   04/05/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   04/06/2023   Conditional Approval   STEVEN LEVITT
  Deputy Shotcrete   04/06/2023   Conditional Approval   CAMERON CHABAN
  Deputy Drilled-In Anchors   04/26/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   05/03/2023   Conditional Approval   CAMERON CHABAN
  Excavation/Setback/Form/Re-Bar   05/03/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   05/11/2023   Conditional Approval   CAMERON CHABAN
  Footing/Foundation/Slab   05/11/2023   Partial Approval   CAMERON CHABAN
  Special/Order Compliance   05/11/2023   Partial Approval   STEVEN LEVITT
  Footing/Foundation/Slab   05/16/2023   Partial Approval   CAMERON CHABAN
  Special/Order Compliance   05/16/2023   Partial Approval   STEVEN LEVITT
  Deputy Reinf. Concrete   05/19/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   06/07/2023   Conditional Approval   STEVEN LEVITT
  Excavation/Setback/Form/Re-Bar   06/07/2023   Partial Approval   JOHN KITCKO
  Deputy Shotcrete   06/08/2023   Conditional Approval   STEVEN LEVITT
  Green Building Rough   06/14/2023   Not Ready for Inspection   CAMERON CHABAN
  Reinforced Concrete Frame   06/14/2023   Partial Inspection   CAMERON CHABAN
  Deputy Shotcrete   06/16/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   06/21/2023   Conditional Approval   CAMERON CHABAN
  Green Building Rough   06/21/2023   Partial Inspection   CAMERON CHABAN
  Reinforced Concrete Frame   06/21/2023   Partial Inspection   CAMERON CHABAN
  Deputy Shotcrete   06/22/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   06/23/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   06/26/2023   Conditional Approval   STEVEN LEVITT
  Deputy Shotcrete   07/07/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   07/13/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   07/13/2023   Conditional Approval   CAMERON CHABAN
  Footing/Foundation/Slab   07/13/2023   Partial Approval   CAMERON CHABAN
  Deputy Steel/Welding   07/18/2023   Conditional Approval   CAMERON CHABAN
  Deputy Steel/Welding   07/19/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   07/20/2023   Conditional Approval   CAMERON CHABAN
  Deputy Steel/Welding   07/20/2023   Conditional Approval   CAMERON CHABAN
  Footing/Foundation/Slab   07/20/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   07/21/2023   Conditional Approval   CAMERON CHABAN
  Deputy Steel/Welding   07/21/2023   Conditional Approval   CAMERON CHABAN
  Deputy Fireproofing   07/26/2023   Conditional Approval   CAMERON CHABAN
  Deputy Fireproofing   07/28/2023   Conditional Approval   JEFFREY DURAN
  Light Gage Steel Frame   07/28/2023   Partial Approval   STEVEN LEVITT
  Deputy Shotcrete   08/01/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   08/02/2023   Conditional Approval   CAMERON CHABAN
  Excavation/Setback/Form/Re-Bar   08/02/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   08/03/2023   Conditional Approval   CAMERON CHABAN
  Deputy Shotcrete   08/03/2023   Conditional Approval   CAMERON CHABAN
  Footing/Foundation/Slab   08/04/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   08/08/2023   Conditional Approval   CAMERON CHABAN
  Green Building Rough   08/25/2023   Partial Inspection   CAMERON CHABAN
  Reinforced Concrete Frame   08/25/2023   Partial Approval   CAMERON CHABAN
  Drywall Nailing   09/08/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   09/15/2023   Conditional Approval   JEFFREY DURAN
  Deputy Reinf. Concrete   09/20/2023   Conditional Approval   CAMERON CHABAN
  Footing/Foundation/Slab   09/20/2023   Not Ready for Inspection   CAMERON CHABAN
  Deputy Reinf. Concrete   09/21/2023   Conditional Approval   STEVEN LEVITT
  Footing/Foundation/Slab   09/27/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   09/29/2023   Conditional Approval   CAMERON CHABAN
  Footing/Foundation/Slab   10/04/2023   Partial Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   10/05/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   10/17/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   10/18/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   10/18/2023   Conditional Approval   JEFFREY DURAN
  Deputy Reinf. Concrete   10/19/2023   Conditional Approval   CAMERON CHABAN
  Deputy Fireproofing   11/02/2023   Conditional Approval   CAMERON CHABAN
  Light Gage Steel Frame   11/03/2023   Partial Inspection   CAMERON CHABAN
  Deputy Drilled-In Anchors   11/16/2023   Conditional Approval   CAMERON CHABAN
  Deputy Reinf. Concrete   11/20/2023   Approved   JEFFREY DURAN
  Green Building Rough   11/20/2023   Not Ready for Inspection   JEFFREY DURAN
  Reinforced Concrete Frame   11/20/2023   Partial Approval   JEFFREY DURAN
  Deputy Reinf. Concrete   11/21/2023   Conditional Approval   CAMERON CHABAN
  Deputy Drilled-In Anchors   12/06/2023   Conditional Approval   CAMERON CHABAN
  Deputy Fireproofing   12/11/2023   Conditional Approval   JOHN KITCKO
  Deputy Reinf. Masonry   02/01/2024   Conditional Approval   JEFFREY DURAN
  Deputy Reinf. Masonry   02/02/2024   Conditional Approval   JEFFREY FULTON
  Deputy Reinf. Masonry   02/05/2024   Conditional Approval   JEFFREY FULTON
  Deputy Reinf. Masonry   02/06/2024   Conditional Approval   JOHN KITCKO
  Deputy Reinf. Masonry   02/07/2024   Conditional Approval   STEVEN LEVITT
  Deputy Reinf. Masonry   02/08/2024   Conditional Approval   JEFFREY DURAN
  Deputy Reinf. Masonry   02/09/2024   Conditional Approval   JEFFREY DURAN
  Deputy Reinf. Masonry   02/15/2024   Conditional Approval   KENNETH ROBERTS
  Deputy Reinf. Masonry   02/16/2024   Conditional Approval   KENNETH ROBERTS
  Deputy Drilled-In Anchors   03/29/2024   Conditional Approval   ROBERT DAVIS
  Excavation/Setback/Form/Re-Bar   04/22/2024   Partial Approval   JOHN KITCKO
  Deputy Reinf. Concrete   04/30/2024   Conditional Approval   ROBERT DAVIS
  Deputy Reinf. Concrete   05/01/2024   Conditional Approval   ROBERT DAVIS